Client:
Vale Canada LimitedLocation:
Ontario, CanadaDuration:
3 YearsScope of Work:
Product:
Redbore 90THREE RAISE DRILLS ON SITE
The Totten Mine raiseboring program consisted of the excavation of raises 6, 8, 12 and 16 feet in diameter, drilling drain lines, and directional drilling. Three raise drills were on site simultaneously for this project; the Redbore 90, Redbore 40, and Redpath 85R.
NOTABLE ACHIEVEMENTS - TOTTEN
13,000 LINEAR FEET DRILLED |
LTI FREE 258,000 HR WORKED |
1,200,000 CU FT OF ROCK EXCAVATED |