Cliente:

Rio Tinto

Lugar:

British Columbia, Canada

Duración:

3 Years and 6 Months

Alcance del trabajo:

Desarrollo minero
Servicios especializados

Redpath's drilling and blasting expertise was deployed at the T2 tunnel project, ensuring a reliable supply of hydroelectric power to Rio Tinto’s aluminum smelter in Kitimat, British Columbia, Canada.

The Kemano T2 Project involved excavating a new 7.6 km portion of tunnel and refurbishing an existing 8.4 km portion of a second tunnel to complete a 16 km long tunnel to the existing penstocks.

Redpath’s involvement focused on the section of tunnel that was excavated by TBM (tunnel boring machine) in the late 80s and early 90s. T2 offered an opportunity to use Redpath’s underground mining methodologies in a civil infrastructure project.

The scope of work consisted of drilling and installing additional ground support, drilling drain holes, pouring concrete in transition areas and spraying shotcrete in designated locations through the downstream section of the tunnel.

The avalanche-prone Kemano region is only accessible by air or water, and Redpath’s experience from harsh climates and remote locations was conducive to the success of the project.

Redpath's involvement in the project concluded in July 2022.

DRILLING AND BLASTING EXPERTISE

DEPLOYED IN CIVIL
INFRASTRUCTURE PROJECT

HARSH CLIMATE AND REMOTE LOCATION

EXPERIENCE CONDUCIVE
TO PROJECT SUCCESS

ENSURING RELIABLE SUPPLY

OF HYDROELECTRIC POWER
TO ALUMINUM SMELTER

 