Cliente:

Goldcorp Inc.

Lugar:

Canadá

Duración:

Ongoing

Alcance del trabajo:

Desarrollo minero
Excavación masiva
Raiseboring

Producto:

Redbore 40, Redbare 50, Redbore 70, Redbore 90

800 m deep borehole shaft, 5.5 m in diameter

Borehole drilling a 800 m shaft at 5.5 m diameter. This shaft will be drilled in two legs, one 400 m, the other 377 m. This project is well underway with the directionally drilled first leg complete and within client specified tolerances. Redpath will equip the shaft with rope guides. A material handling wins, ore bins, ventilation raises and ore passes are also part of this scope.

Project Image - Musselwhite Mine - 3,000m Development

3,000m Development

Project Image - Musselwhite Mine - LTI Free Since Start Of Project

LTI Free Since Start Of Project

Project Image - Musselwhite Mine - 22,000m3 Mass Excavation

22,000m3 Mass Excavation