Cliente:
Goldcorp Inc.Lugar:
CanadáDuración:
OngoingAlcance del trabajo:
Producto:
Redbore 40, Redbare 50, Redbore 70, Redbore 90800 m deep borehole shaft, 5.5 m in diameter
Borehole drilling a 800 m shaft at 5.5 m diameter. This shaft will be drilled in two legs, one 400 m, the other 377 m. This project is well underway with the directionally drilled first leg complete and within client specified tolerances. Redpath will equip the shaft with rope guides. A material handling winze, ore bins, ventilation raises and ore passes are also part of this scope.
NOTABLE ACHIEVEMENTS - MUSSELWHITE
3,000m DEVELOPMENT |
LTI FREE SINCE START OF PROJECT |
22,000m3 MASS EXCAVATION |